Skip to main content Skip to office menu Skip to footer
Capital IconMinnesota Legislature
Skip Navigation Links > >

Mandate Details

Description: Summary of commission's decision on an application for a certificate of need for authorization of any additional dry cask storage or expansion or establishment of an independent spent fuel storage facility at a nuclear generation facility
Law: 2003 Minn. Laws 1st Spl. Sess. Chap. 11 Art. 1 Sec. 2 Subd. 3
Statute: 116C.83 Subd. 3
Agency(ies)/Supplier(s): Minn. Public Utilities Commission
Due Date: 01/15/2010
Frequency: Other
Subjects: Energy Issues - Nuclear Energy
Note: This report is contingent upon an expansion request, and involves a stay of a decision by the PUC until June 1 following the next regular annual session of the legislature, the report would be due by Jan. 15 of the year of that session.

Item(s) Received

TitlePublisher(s)Publication DateCoverageDate ReceivedReport LinkCall #
Report of the Minnesota Public Utilities Commission's Decision Concerning Additional Spent Nuclear Fuel Storage at the Monticello Nuclear Generating Plant Independent Spent Fuel Storage Installation (ISFSI) Minn. Public Utilities Commission December 28, 2023 12/28/2023 23-2045.pdf
TD899.A8 L443 2023
Supplemental Filing to the Legislative Report Concerning Certificate of Need for Additional Dry Cask Storage Facility, Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage ... Minn. Public Utilities Commission January 28, 2010 01/28/2010 10-0153.pdf
TD899.A8 L443 2010
Legislative Report Concerning Certificate of Need for Dry Cask Storage Facility, Prairie Island Nuclear Generating Plant Independent Spent Fuel Storage Installation Minn. Public Utilities Commission January 15, 2010 01/21/2010 10-0066.pdf
TD899.A8 L442 2010
Legislative Report Concerning Certificate of Need for Dry Cask Storage Facility Minn. Public Utilities Commission January 3, 2007 01/04/2007 07-0016.pdf
TD899 .A8 L44 2007